Ritz-Carlton is rising

Resort developer makes lemonade from economy's 'lemon'

By Brian J. Pedersen, Arizona Daily Star
Photo by Mamta Popat / Arizona Daily Star
Jul 25, 2008

Though the struggling U.S. economy has affected quite a few big-name developments locally, the slowdown doesn't seem to be hurting one of the Northwest Side's most ambitious projects.

In fact, those affiliated with construction of the Ritz-Carlton resort in Dove Mountain say, other projects' losses are their gains.

"As other projects don't go forward, it creates more resources for us as we do go forward," project manager Richard Frazee said, just before slapping on a hard hat to wander through a bustling construction area. "We have over 500 workers in here on a daily basis."

The $500 million, 850-acre project, which was officially announced as being a Ritz-Carlton last October, is more than half done, officials say.

The four-story, 250-room Ritz-Carlton hotel is about 50 percent complete, Frazee said, while the clubhouse attached to the 36-hole golf club is 70 percent done.

The first 27 golf holes are complete, said Casey Bolinger of co-developer Greenbrier Southwest Corp., although revegetation continues along the edges of holes to help blend the grass into the natural desert landscape that surrounds them.

Eighteen of those holes, all of which were designed by legendary golfer Jack Nicklaus, will be the site of the World Golf Championships-Accenture Match Play Championship in February.

The clubhouse is expected to open in mid-January, said Tim Bolinger of Scottsdale-based Greenbrier Southwest, which is developing the 850-acre project along with Tucson-based Cottonwood Properties.

"If we weren't doing the hotel, the clubhouse itself would be considered a major project," Tim Bolinger said.

The hotel itself is expected to open in October 2009, though reservations for group outings are already being taken.

"The hotel is coming into the Ritz-Carlton system as we speak," Tim Bolinger said.

The project also calls for a 324-house residential development, called The Residences at the Ritz-Carlton.

Casey Bolinger said two of three model homes are finished, and a third — near the golf clubhouse — will be ready when the Ritz-Carlton begins actively marketing the houses this fall.

About the Ritz-Carlton
  • Developers: Cottonwood Properties of Tucson and Greenbrier Southwest Corp. of Scottsdale
  • Project area: 850 acres
  • Cost: $500 million (estimated)
  • Number of people working daily on construction: About 500

The Ritz-Carlton, Dove Mountain Hotel and Spa

  • Description: Four-story hotel, 335,000 square feet; 250 rooms including 25 detached casitas
  • Projected opening: October 2009.

The Ritz-Carlton, Dove Mountain Golf Club

  • Description: 36 holes (27 are complete)
  • Projected opening: January

The Residences at The Ritz-Carlton, Dove Mountain

  • Description: 324 houses, priced from $1.5 million and $3.5 million; land for custom-home sites is between $750,000 and $1.8 million.
  • Projected opening: To be announced
top